April 21, 2012
So, I have recently been the master of taking pictures and not uploading them to the blog. So I'm running about a week behind. Also, the blog has a crazy new format, so hopefully all looks well.
Alok has been busy laying the black and white marble tile in the kitchen. This is the tile that he picked out because he would "regret it forever" if we didn't buy it ;-) Here it is:
I also attempted to take additional pictures of some of the painting, but it isn't showing as well (of course). If you look straight ahead, you'll see a radiator in the bookcase. We are getting those removed.
Front parlor
Master bath
Part of the kitchen with newly painted trim. Looking sooo much better!
In fun news, look at the space between the original floors and drywall. Hmmm...... plaster is much thicker:
The attic floor is coming along quickly:
Attic bathroom- Has been tiled (needs a bit of work) and then the bathtub needs to be painted.
So, the question still remains, when are we moving in? Answer: Who knows!
What is still on our to-do list:
1) Finish the laid tile (e.g., grout, seal, etc): attic bathroom, apartment bathroom, bathroom under the stairs, and kitchen tile
2) Paint the rest of the kitchen, kitchen cabinets, butler pantry cabinet, apartment bathroom, hallway bathroom, yellow bedroom
3) Put in the stained glass window
4) Fix the stairs
5) Re-paint all window frames/seal them... only 61 to go!
6) Clean up all the crazy stuff that's laying around
7) Kitchen appliances installed/ all bathroom fixtures in the ones we're doing
8) Get the laundry room ready
Big things that will continue/wait:
1) Siding/outdoor painting (we just spent 1 gazillion $$ at Sherwin Williams, so this will somewhat happen this summer)
2) Kitchen countertops (we may do cheap ones now)
3) Apartment floor (lay new wood)
4) All trim, etc to close up the 2 inch gaps in our floors
5) master bath
6) hallway bath
7) Alok's office/bath
8) Yellow bedroom floor
Not to bad, right ;-)
Jessica